Project Deliveryconcept
Construction Manager roles: CM-as-Advisor vs CM-as-Constructor (CM at Risk)
One-line orientation
A CM as Advisor gives the owner advice but does not hold the construction contracts. A CM as Constructor acts as the builder, holds the trade contracts, and carries the construction risk defined by its agreement.
Key points
-
CM-as-Advisor / CM-as-Agent (CMa):
- Acts as the owner’s representative during design and construction.
- Provides expertise in scheduling, cost estimating, constructability review, and bid-package coordination.
- Does not hold any construction contracts — the construction contracts are the owner’s. The owner may hold multiple prime contracts with the trades, or retain one general contractor; the CMa advises across either arrangement.
- Carries no construction risk; compensated with a fee (advisory / agency role only).
- Architect-of-record relationship is unchanged; architect still administers the construction contract.
-
CM-as-Constructor / CM at Risk (CMc):
- Engaged early in the design process — typically alongside the architect — to provide design-phase input.
- Transitions to acting as the general contractor during construction: holds all trade contracts, manages subcontractors, and self-performs or subcontracts all work.
- Carries construction cost and schedule risk within the agreed scope. Approved contract changes may adjust that risk.
- Contract is typically structured as a Guaranteed Maximum Price (GMP). Cost risk depends on the agreed scope, allowances, contingencies, contract adjustments, and owner changes.
- More expensive than a traditional competitively bid GC because there is no competitive GC procurement.
CM-as-Advisor vs CM-as-Constructor: who holds the trade contracts
Same three parties on the same tier — the models differ in which of them the trades hang from, and in which general conditions govern.
View diagram Hide diagram
Scroll horizontally to explore
Document numbers are drawn without year suffixes; the numbers are stable, the editions are not.
Confusions / comparison
| CM-as-Advisor / CM-as-Agent | CM-as-Constructor (CM at Risk) | |
|---|---|---|
| Role | Owner’s representative; advisory only | General contractor with early design-phase involvement |
| Holds trade contracts? | No — the owner holds them (multiple primes, or one GC) | Yes — CMc holds all subcontracts |
| Carries construction risk? | No | Yes (cost + schedule) |
| Compensation | Fee for advisory services | Construction contract (typically GMP) |
| Engaged when | Design or pre-construction | Early — often alongside architect |
| Effect on cost | Owner retains control; no premium for GC role | More expensive than competitive GC bid; no competitive GC procurement |
| GMP typical? | No | Yes |
Related
→ Design-Bid-Build (pp-delivery-design-bid-build): the baseline DBB framework CMa modifies · Design-Build and IPD (pp-delivery-designbuild-ipd): other early-collaboration delivery models · Cross-method comparison (pp-delivery-method-comparison): CMa and CMc in the full delivery method matrix.