Project Deliveryconcept
Design-Bid-Build: traditional sequential delivery and contract variants
One-line orientation
Design-Bid-Build is the default sequential delivery method — owner hires architect first, then competitively bids construction — and is tested because its contract structure, cost certainty trade-offs, and architect liability limits are foundational ARE knowledge.
Key points
- Sequence: Design (complete CDs) → Bid (competitive or negotiated) → Build. Owner holds separate contracts with the architect and the general contractor.
- Competitive low-bid (traditional lump-sum): Open to any qualified contractor. Owner receives a fixed contract price before construction starts — strong cost certainty. Trade-off: slower (no design/construction overlap), and the adversarial dynamic of price competition can reduce collaboration.
- Cost-plus-fixed-fee:
- Payment — actual project costs + predetermined fee
- Benefit — scope flexibility without pressure to protect a lump sum.
- Risk — owner bears cost overruns and has no locked total price
- Negotiated Select Team: Owner chooses a contractor through negotiation rather than open bidding. Contractor may be brought in during later design phases, enabling early constructability input. Early contractor input may help the schedule and constructability, but negotiated selection does not guarantee higher quality and gives up open price competition.
- Architect’s role and liability boundary: The architect provides design and construction administration; the architect is not liable for the contractor’s means and methods. Construction means/methods — how work is physically executed — remain solely the contractor’s responsibility.
Confusions / comparison
| Variant | Bidder pool | Price set when | Owner cost risk | Speed | Collaboration |
|---|---|---|---|---|---|
| Lump-sum competitive bid | Open (any qualified contractor) | Before construction (fixed) | Low | Slowest | Low (adversarial) |
| Cost-plus-fixed-fee | Negotiated / open | Cost is running total; fee fixed | Higher (owner bears overruns) | Moderate | Moderate |
| Negotiated Select Team | Pre-selected / negotiated | Typically negotiated GMP or lump sum | Moderate | Faster | Higher (early contractor input) |
Related
→ Bidding variants (pp-delivery-bidding-variants): open competitive vs invited vs negotiated vs phased/fast-track bid types · Construction Manager roles (pp-delivery-construction-manager): how CM variants modify the DBB structure · Cross-method comparison (pp-delivery-method-comparison): DBB ranked against CMa, CMc, DB, and IPD across owner priorities.