Basic, Supplemental, and Additional Services under B101: the three service tiers

One-line orientation

B101 defines three service tiers with different timing, authorization, and fee implications — the supplemental-vs-additional distinction is the most frequently tested trap in this topic.

Key points

  • Basic Services:
    • The five standard phases: SD, DD, CD, Bidding/Procurement, CA.
    • Included in the base fee; the architect must provide them under the signed agreement.
    • No additional authorization or compensation required to proceed through the phases.
  • Supplemental Services:
    • Services beyond the five phases that are agreed upon and written into the contract at signing.
    • Pre-priced: fee and scope are defined before the project begins.
    • Examples can include sustainable design consulting, measured drawings, specialized programming, on-site project representation, or other extra scopes when the parties agree up front to include them.
    • Designated in the Section 4.1 table of B101-2017 (described there or in an attached exhibit such as a B2xx scope document) before signing.
  • Additional Services:
    • Arise after the contract is signed due to changed conditions, owner requests, or unforeseen events, and fall under Section 4.2 of B101-2017 — the counterpart to the Section 4.1 table.
    • Additional Services generally require prompt notice and owner authorization. For specified services needed to avoid delay, B101 may allow the architect to begin and notify the owner promptly; the owner can direct the architect not to continue.
    • Compensated separately — outside and above the base fee.
    • Common triggers: owner-requested scope changes, extra evaluations, extra services caused by delay or changed project conditions, or a service such as programming / certification support / on-site representation that was not selected at signing but is requested later.
    • The architect must notify the owner when an Additional Service is needed; the owner then authorizes (or declines) in writing.

Confusions / comparison

TierWhen definedWritten into contract?Extra fee?Owner authorization to proceed?
Basic ServicesAt signingYes — the five phasesNo (included in base fee)No
Supplemental ServicesAt signingYes — in Sec. 4.1 table or B2xx exhibitYes (pre-agreed amount)No — already authorized at signing
Additional ServicesAfter signingNo — arise later or are authorized by amendmentYes (negotiated when authorized)Generally yes; check B101’s notice-and-delay exception
  • pp-aia-b101-owner-architect — full B101 article structure, including Article 4 Additional Services
  • pp-aia-document-families — B-series overview and where B2xx exhibits fit
  • pp-aia-c401-architect-consultant — how consultants handle additional service requests under C401