Schedulinginsight
Fast-track scheduling: overlapping design and construction via phased bid packages
One-line orientation
Fast-track compresses the project schedule by overlapping design and construction through phased bid packages, but it trades schedule savings for higher change risk — and it is a scheduling strategy, not a delivery method.
Key points
- Definition: fast-track = overlapping design phases with construction by issuing early bid packages for portions of the work (foundation, structural steel, envelope) before the overall design is complete.
- How it works: the project is broken into sequential bid packages. Package 1 (e.g., sitework/foundation) is designed and bid first; construction on that package starts while design continues on Package 2, and so on.
- Schedule impact: total project duration is compressed because design and construction proceed in parallel rather than in series.
- Risk profile:
- Change risk rises — decisions made in later design packages may conflict with already-built work, forcing costly changes or rework.
- Coordination gap risk — incomplete design integration between packages can create conflicts at interfaces (structure vs. MEP, envelope vs. interior).
- The team should consider added contingency for fast-track uncertainty; the amount and where it is held depend on the project and contract.
- Scheduling tool: The Critical Path Method (CPM) is useful for tracking dependencies and the critical path among overlapping packages, but it is not required for every fast-track project.
- Delivery method pairing: fast-track is most common with CMc (Construction Manager as Constructor) delivery — the CM is involved early in design to advise on phasing, sequencing, and package content. It can also pair with Design-Build.
- Not a delivery method: fast-track describes schedule structure, not the contractual relationship between parties.
Fast-track: a series of bid packages, each its own design–bid–build
Each bid package runs its own design → bid → construction, released in sequence so early construction overlaps the design of later packages.
View diagram Hide diagram
Scroll horizontally to explore
- Design
- Bid
- Construction
Fast-track is a scheduling strategy, not a delivery method. CPM is useful for tracking dependencies, but the scheduling method is a project decision.
Overlap raises coordination, change, and rework risk; the project team decides the scheduling method and appropriate contingency.
Confusions / comparison
| Traditional (linear) | Fast-track (overlapped) | |
|---|---|---|
| Schedule | Longer — phases in series | Shorter — design and construction overlap |
| Cost certainty | Higher — full design before bid | Lower — incomplete design at construction start |
| Change / rework risk | Lower | Higher |
| Scheduling approach | Often simple to show on a Gantt chart | CPM is useful for complex dependencies; project team selects the method |
| Common delivery pairing | Design-bid-build | CMc, Design-Build |
Related
→ pp-scheduling-methods-cpm (this module): how CPM can track fast-track dependencies · pp-construction-payment-basis (this module): fast-track commonly pairs with GMP/CMc payment structure · ProPractice — project delivery methods: CMc delivery (AIA A133/B133) is a common fast-track vehicle.
Spotted an issue with this card? Tell us →
ratings update your review schedule ·
Round complete