Project Deliveryconcept
Owner-contractor payment structures: stipulated sum, cost-plus, GMP, unit price
One-line orientation
The owner-contractor payment structure determines who absorbs cost risk — the contractor or the owner — and understanding each type is essential for both PjM project-delivery questions and CE contract-administration questions.
Key points
- Stipulated sum (lump sum) — AIA A101:
- Contractor agrees to complete the work for a single fixed amount.
- Contractor bears the risk — if actual costs exceed the sum, it comes out of the contractor’s profit.
- Owner benefits from cost certainty; requires a fully designed project before contract is signed.
- Alternates, allowances, and unit prices can be embedded within a stipulated sum contract to handle known unknowns.
- Cost-plus-fee:
- Owner pays the contractor’s actual cost of work plus an agreed fee (fixed fee, percentage, or other).
- Owner bears the risk — no ceiling on total cost.
- Requires open-book accounting and owner trust; appropriate when scope cannot be fully defined.
- Guaranteed Maximum Price (GMP) — AIA A133 with CMc:
- A GMP is a cost-plus contract with a cap on the agreed scope and cost basis. Approved contract changes may adjust the cap.
- Savings below the GMP go to the owner unless the contract expressly provides a sharing formula.
- GMP is established based on design documents available at the time — includes allowances for incomplete scope.
- Pre-GMP estimates by the CMc are not guaranteed; the GMP itself is the binding ceiling.
- Commonly used with the Construction Manager as Constructor (CMc) delivery method.
- Unit prices:
- Used when the quantity of work cannot be determined in advance (earthwork, piling, demolition of unknown extent).
- A price per unit is agreed; the total payment adjusts based on actual quantities.
- Often embedded within a stipulated sum or GMP contract for specific line items.
- Retainage: the owner withholds part of each progress payment as an incentive to finish the work. The agreement and applicable law control the percentage and release date; retainage may remain until Final Completion.
Who bears the cost-overrun risk
Overrun risk shifts toward the owner moving left.
View diagram Hide diagram
Scroll horizontally to explore
A GMP (guaranteed maximum price) caps the owner’s exposure, and unit-price risk is shared because the quantity varies.
Confusions / comparison
| Payment basis | Who bears overrun risk | Cost certainty for owner | When used |
|---|---|---|---|
| Stipulated sum | Contractor | High — fixed price | Fully designed project, competitive bid |
| Cost-plus-fee | Owner | Low — open-ended | Ill-defined scope; high owner trust |
| GMP (cost-plus with cap) | Owner up to cap; contractor above cap | Medium — ceiling known, actual costs vary | CMc delivery; phased or fast-track projects |
| Unit price | Shared — quantity unknown | Partial — price/unit fixed, total varies | Earthwork, piling, work of unknown quantity |
Related
→ pp-architect-compensation-methods (this module): the parallel owner-architect fee structures · pp-fast-track-scheduling (this module): fast-track projects commonly use GMP + CMc delivery · ProPractice — AIA A101 / A133: the AIA document pair for each payment structure.
Spotted an issue with this card? Tell us →
ratings update your review schedule ·
Round complete