Basic, Supplemental, and Additional Services under B101: the three service tiers
One-line orientation
B101 defines three service tiers with different timing, authorization, and fee implications — the supplemental-vs-additional distinction is the most frequently tested trap in this topic.
Key points
- Basic Services:
- The five standard phases: SD, DD, CD, Bidding/Procurement, CA.
- Included in the base fee; the architect must provide them under the signed agreement.
- No additional authorization or compensation required to proceed through the phases.
- Supplemental Services:
- Services beyond the five phases that are agreed upon and written into the contract at signing.
- Pre-priced: fee and scope are defined before the project begins.
- Examples can include sustainable design consulting, measured drawings, specialized programming, on-site project representation, or other extra scopes when the parties agree up front to include them.
- Designated in the Section 4.1 table of B101-2017 (described there or in an attached exhibit such as a B2xx scope document) before signing.
- Additional Services:
- Arise after the contract is signed due to changed conditions, owner requests, or unforeseen events, and fall under Section 4.2 of B101-2017 — the counterpart to the Section 4.1 table.
- Additional Services generally require prompt notice and owner authorization. For specified services needed to avoid delay, B101 may allow the architect to begin and notify the owner promptly; the owner can direct the architect not to continue.
- Compensated separately — outside and above the base fee.
- Common triggers: owner-requested scope changes, extra evaluations, extra services caused by delay or changed project conditions, or a service such as programming / certification support / on-site representation that was not selected at signing but is requested later.
- The architect must notify the owner when an Additional Service is needed; the owner then authorizes (or declines) in writing.
Confusions / comparison
| Tier | When defined | Written into contract? | Extra fee? | Owner authorization to proceed? |
|---|---|---|---|---|
| Basic Services | At signing | Yes — the five phases | No (included in base fee) | No |
| Supplemental Services | At signing | Yes — in Sec. 4.1 table or B2xx exhibit | Yes (pre-agreed amount) | No — already authorized at signing |
| Additional Services | After signing | No — arise later or are authorized by amendment | Yes (negotiated when authorized) | Generally yes; check B101’s notice-and-delay exception |
Related
- pp-aia-b101-owner-architect — full B101 article structure, including Article 4 Additional Services
- pp-aia-document-families — B-series overview and where B2xx exhibits fit
- pp-aia-c401-architect-consultant — how consultants handle additional service requests under C401
Spotted an issue with this card? Tell us →